HUBCO Reports Major Transformer Fault at China Power Hub Plant, Unit 1 Faces Forced Outage

The Hub Power Company Limited (HUBCO) has disclosed a major operational issue at its China Power Hub Generation Company Limited (CPHGC) power plant, announcing that Unit 1 will remain unavailable for electricity generation following a serious electrical fault in its main transformer.

In a disclosure submitted to the Pakistan Stock Exchange (PSX) on October 21, 2026, HUBCO stated that the main transformer of Unit 1 had sustained a serious electrical fault. The unit has subsequently been placed under a forced outage to allow technical teams to investigate the issue and carry out the necessary repair work.

The affected CPHGC facility is a 1,320-megawatt (MW) imported coal-fired power plant comprising two generating units, each with an approximate capacity of 660 MW. The plant also has an integrated coal jetty and is located in Hub Tehsil, Tehsil Gaddani, District Lasbela, Balochistan.

According to the disclosure, CPHGC owns and operates the power plant through a joint venture between Hub Power Holdings Limited (HPHL), a wholly owned subsidiary of HUBCO, and China Power International (Pakistan) Investment Limited.

Unit 1 Unavailable During Investigation and Repairs

The transformer fault has resulted in the temporary suspension of electricity generation from Unit 1. The forced outage is intended to provide the company with time to investigate the technical problem and determine the necessary corrective measures.

Since Unit 1 has an installed generation capacity of approximately 660 MW, its unavailability could affect the plant’s overall electricity generation capacity while the fault remains unresolved.

However, HUBCO’s disclosure did not provide a specific timeline for completing the investigation or restoring the affected unit to commercial operations.

Implications for HUBCO and the Power Sector

The development is significant because the CPHGC power plant is a major component of Pakistan’s electricity generation infrastructure. The temporary unavailability of one generating unit reduces the facility’s available generation capacity by approximately half of its installed capacity.

The eventual impact will depend on how long the forced outage continues and the availability of other electricity generation sources within the national power system.

For investors, the development is an important operational update that may be relevant when assessing HUBCO’s power generation activities and the performance of its associated investments.

Company Disclosure to PSX

HUBCO issued the notification in accordance with Sections 96 and 131 of the Securities Act, 2015, and Rule 5.6.1(a) of the Pakistan Stock Exchange Rule Book.

The company requested the stock exchange to disseminate the information to its members. The disclosure was signed by Faiza Kapadia Raffay, Company Secretary of The Hub Power Company Limited.

Conclusion

The serious transformer fault at CPHGC’s Unit 1 has resulted in a forced outage of approximately 660 MW of generation capacity. HUBCO has confirmed that the company is investigating the fault and working toward resolving the issue.

The duration of the outage and the timing of the unit’s return to service will be important factors to monitor in the coming days, particularly for investors and stakeholders following Pakistan’s power sector.